LIGHTING RETROFIT/ENERGY
MANAGEMENT SYSTEM/COGENERATION
 |
Industrial facility retrofit strategy for a high-tech
outdoor gear manufacturer in Orange County
This ultra-modern 500,000 square foot manufacturing
facility was constructed in 1996. The facility
serves as both a corporate headquarters, flagship
property, manufacturing facility, data center
and warehouse. The next>edge energy audit process
revealed the following opportunities - Lighting
Retrofit, Energy Management System Upgrades and
Cogeneration. |
Lighting
The office areas in this building are currently equipped
with T8 lamps and electronic ballasts. However, despite
the presence of these fairly modern lighting systems
in office areas, the warehouse and manufacturing areas
have a mixture of HID lighting and T12 fluorescent strip
fixtures.
A retrofit of the existing office T8 fixtures with
second generation lamps and ballasts will provide an
attractive rate of return, particularly when utility
incentives are included. next>edge has developed
a scope of work that takes full advantage of reflectors
and delamping. The warehouse areas will be retrofitted
with a combination of T8 lamp and ballast systems for
the strip fixtures and the installation of new T5 high
bay fixtures in place of the existing HID lighting.
The HID light fixture replacement is perhaps the most
dramatic initiative, with a per fixture wattage reduction
from 418 watts to 244 watts while maintaining light
levels, extending lamp life and lumen maintenance, and
the improvement of color rendering.
EMS Upgrades
There is an existing, modern DDC control system in place
for operation of the HVAC system. However, all of the
key operational decisions are still made manually. There
are a number of variable frequency drives, but a lack
of adequate sequences resulting in these devices running
at full speed a majority of the time. The chilled water
pumps are equipped with variable frequency drives, but
the piping system is equipped with a bypass that precludes
operation as a variable flow system. A great deal of
pumping energy is therefore wasted.
next>edge recommends piping modifications which
can be done at a relatively small capital cost. The
basic mechanical system elements required for energy
efficiency already exist. Minor mechanical changes coupled
with sequence development and recommissioning of the
DDC system will help the customer finally realize the
return on his original investment. The installation
serves as a case in point for the need to perform commissioning.
There are a number of similar projects that, along with
the variable flow conversion measure, all have simple
paybacks in the 1.5 to 3 year range. Finishing the system
design, installation and commissioning process appears
to be the right direction for this facility, taking
the site to where it should have been all along as a
recently constructed building.
Cogeneration
The facility is 24x7 operation and has massive electric
and thermal needs. The site is also somewhat remote,
leaving room for an on-grade installation without noise
concerns. Therefore, the site is an excellent cogeneration
candidate.
Recommended cogeneration project is a 750 kW prime
mover, a 3,000 MBH hot water recovery boiler and a 175-ton
absorption chiller. Hot water and chilled water will
interconnect to the central plant. The engine gen-set
will be a reciprocating engine set up for operation
with natural gas at a low RPM. Selecting this equipment
carefully will assure many years of reliable service.
The cogeneration project has a longer payback term
that the other recommended measures. We are recommending
that the customer consider the possible benefits of
combining this project with a backup system serving
the existing data center - a critical load. The project
economics will be boosted substantially by the added
consideration of backup power.
Commissioning
In addition to all the lighting and mechanical upgrades,
next>edge will complete an intensive project commissioning
process. More than 50% of the energy savings produced
by these projects are often achieved during this phase.
Commissioning will provide EMS and HVAC system optimization,
primarily focusing on overall system kW/Ton. For the
cogeneneration plant, commissioning will be focused
on ensuring that the new systems are providing beneficial
energy to the existing facility, consistent with predicted
results and manufacturer ratings.
|